The Short Answer
Ask for a separate release time for each activity. A dry-looking surface or permission to walk on the floor does not establish that it is ready for loaded forklifts, parked cars or cleaning chemicals.
Plan Separate Release Times
Product data sheets may distinguish foot traffic, light traffic and full cure at different temperatures. Ask your installer what each term permits for the complete system on your slab. Confirm in writing whether the light-traffic category covers your loaded forklifts before scheduling their return. Get separate instructions for the first wet cleaning or chemical exposure if the data sheet does not specify that use.
Warehouse Example: Reopen In Phases
A warehouse needs staff access to dispatch before loaded forklifts can return to the main aisle. Divide the work into zones. For each zone, record when the final coat was completed and identify the pedestrian route, loaded forklift route and first scheduled scrubber pass. Keep the alternate route available if a zone’s release moves.
Have the installer confirm three separate release times in writing. Give the shift lead responsibility for removing barriers for each activity after approval. If the slab near a loading door runs cooler than planned, ask the installer to reassess that zone before reopening it.
Read The Warehouse Planning GuideWinter Garage Example: Walking And Parking
A homeowner wants to walk through the garage to reach the house and park there again before the next snowfall. Ask the installer to confirm the slab temperature as well as the air temperature, especially near the overhead door. Agree how the garage conditions will be maintained during cure.
Plan alternate parking and ask for separate dates and times for walking, parking, and the first wet cleaning. If overnight temperatures fall below the conditions used for scheduling, check with the installer before bringing the car back or allowing snowmelt onto the floor.
Read The Garage Flooring System ComparisonWhat To Get At Handover
- The installed system and when the final coat was completed in each zone.
- The site conditions used to set the schedule and who to contact if they change.
- Release dates and times for walking, parked cars or loaded equipment, and the first approved cleaning.
- Any temporary restrictions and the cleaning products and equipment approved for the finished floor.
For the steps leading up to handover, see How A Resinous Floor Is Installed.